PERT activity time is calculated using the formula (Optimistic Time + 4 * Most Likely Time + Pessimistic Time) / 6 is Expected Time.

Avatar
Discard
Best Answer

true

Avatar
Discard
Best Answer

T

Avatar
Discard
Author Best Answer

?

Avatar
Discard
Best Answer

Answer: True