In a minimization problem, what does a positive reduced cost imply about a non-basic decision variable?

Avatar
Discard
Best Answer

In a minimization problem, a positive reduced cost means that increasing a non-basic decision variable from zero would increase the objective function value, so it would not improve the current solution.

Avatar
Discard
Best Answer

In a linear programming minimization problem, a positive reduced cost indicates that forcing a non-basic decision variable into the optimal solution (increasing its value from zero) would increase the total objective function value by that reduced cost per unit, thereby making the solution worse (less optimal).