A factory has 100 hours of labor available. Product X requires 4 hours per unit and Product Y requires 2 hours per unit. Write the labor constraint.
This question has been flagged
1
Reply
57
Views
4X + 2Y ≤ 100
Divide everything by 2:
2X + Y ≤ 50
So the simplified labor constraint is:
✅ 2X + Y ≤ 50
If producing only one product:
- Only X: 100 ÷ 4 = 25 units
- Only Y: 100 ÷ 2 = 50 units