Infeasibility in the Big M method is recognized when the simplex algorithm reaches an optimal tableau, but at least one artificial variable remains in the basic solution with a strictly positive value

Avatar
Discard

In the Big M method, infeasibility is recognized when an artificial variable remains positive in the final solution, meaning the constraints are incompatible and no feasible solution exists.